Total Permits
1,413
Active additions & alterations
Total Declared Value
$1.37B
Combined permit value
Average Project Value
$1.04M
Per permit
Largest Single Permit
$75M
2200 Yonge St, Toronto
Peak Month
Apr 2026
336 permits · $425M
Top City
Toronto
93% of all permits
Permits by City
Value by City
Monthly Volume — Permits Issued
202
Dec
249
Jan
266
Feb
297
Mar
336
Apr
63
May*
* May 2026 data is partial — permits still being filed
Permit Type Breakdown
Top 30 Projects by Declared Value Dec 2025 – May 2026
| # | Address | Type | Issued | Permit Value | Status |
|---|---|---|---|---|---|
| 1 | 2200 Yonge StToronto Building renovation incl. interior demolition, curtain wall modernization, elevator modernization & roof replacement (levels 1–17). |
Addition/Alt | Apr 8, 2026 | $75,000,000 | Open |
| 2 | 900 Bay StToronto Interior fit-out — floors 3 to 16. |
Addition/Alt | Apr 8, 2026 | $44,808,269 | Open |
| 3 | 40 Bay StToronto Renovation to public galleria, Sher Club balcony, east suites & elevator lobby. |
Addition/Alt | Apr 27, 2026 | $40,000,000 | Open |
| 4 | 81 Bay StToronto Interior alterations — fit-out floors 8 & 9 for CIBC tenant. |
Addition/Alt | Dec 15, 2025 | $30,000,000 | Open |
| 5 | 900 Bay StToronto Interior fit-out — floors 17 to 24. |
Addition/Alt | Apr 10, 2026 | $29,786,065 | Open |
| 6 | 2180 Yonge StToronto Renovation incl. basement, ground floor lobby, 3rd floor, elevator & curtain wall modernization. |
Addition/Alt | Mar 3, 2026 | $28,000,000 | Open |
| 7 | 198 New Toronto StToronto New granulated sugar silo facility with truck bay; warehouse renovation for future equipment. |
Addition/Alt | May 4, 2026 | $27,000,000 | Open |
| 8 | 555 University AveToronto New Cardiac Clinic & Diagnostic Unit on L9; HVAC upgrades, window replacement (hospital). |
Addition/Alt | Feb 13, 2026 | $26,075,300 | Open |
| 9 | 124 Edward StToronto Interior alteration — UofT School of Dentistry: lobby, clinics 1 & 2, elevator & corridors. |
Addition/Alt | Mar 2, 2026 | $24,000,000 | Open |
| 10 | 25 The West MallToronto Interior demolition; new mechanical shafts, passenger & freight elevators, new escalator at basement/level 1. |
Addition/Alt | Apr 9, 2026 | $20,000,000 | Open |
| 11 | 199 Bay StToronto Interior alterations to commercial office & retail banking (CIBC Commerce Court West). |
Addition/Alt | Mar 16, 2026 | $20,000,000 | Open |
| 12 | 2075 Bayview AveToronto Interior alterations — replacement of x-ray system. |
Addition/Alt | Jan 29, 2026 | $19,000,000 | Open |
| 13 | 30 Bond StToronto Interior alteration L15 — relocate NICU; new AHU on roof with service stair and platform. |
Addition/Alt | Feb 24, 2026 | $18,000,000 | Open |
| 14 | 6 Spadina RdToronto Replace existing subway ventilation equipment — fans, shaft dampers & silencers. |
Addition/Alt | Apr 29, 2026 | $17,500,000 | Open |
| 15 | 1901 Mount Pleasant RdToronto Addition and alterations — electrical, structural, mechanical & plumbing. |
Addition/Alt | Apr 2, 2026 | $17,000,000 | Open |
| 16 | 40 King St WToronto Interior alterations — unit 2000–2200. |
Addition/Alt | Dec 19, 2025 | $16,000,000 | Open |
| 17 | 483 Bay StToronto Interior alterations to office — levels 4, 5, 9, 10. |
Addition/Alt | Feb 19, 2026 | $16,000,000 | Open |
| 18 | 2535 Gerrard St EToronto 1,749 m² homeless shelter — renovation of former warehouse + addition of 22 bedsitting rooms (81 adults). |
Addition/Alt | Feb 27, 2026 | $15,000,000 | Open |
| 19 | 25 York StToronto New meeting spaces, open office areas, town hall space, kitchenettes & reception. |
Addition/Alt | Jan 2, 2026 | $15,000,000 | Open |
| 20 | 141 Bay StToronto 47th floor — new open workspace, enclosed offices, meeting rooms & cafe stations. |
Addition/Alt | Feb 2, 2026 | $15,000,000 | Open |
| 21 | 199 Bay StToronto Exterior alterations — forecourt & courtyard landscape, waterproofing remediation below pavers. |
Addition/Alt | Dec 10, 2025 | $15,000,000 | Open |
| 22 | 1 Adelaide St EToronto Interior renovation — floors 11, 12 & 14 including new stair opening. |
Addition/Alt | Jan 27, 2026 | $15,000,000 | Open |
| 23 | 2217 Kingston RdToronto Ground floor retail fit-out — specialty millwork for Indigekwe Space (room 118). |
Addition/Alt | Dec 2, 2025 | $14,900,000 | Open |
| 24 | 79 Wellington St WToronto Interior alterations — floor 33 (Torys LLP). |
Addition/Alt | Apr 14, 2026 | $13,598,076 | Open |
| 25 | 8 King St EToronto Interior alteration — unit 1200 (Peloton Capital Management). |
Addition/Alt | Mar 30, 2026 | $13,000,000 | Open |
| 26 | 333 Bay StToronto Interior alteration to Group D occupancy — interconnected floor space (alternative solution). |
Addition/Alt | Dec 18, 2025 | $12,500,000 | Open |
| 27 | 161 Bay StToronto Interior alterations to existing office. |
Addition/Alt | Feb 26, 2026 | $12,000,000 | Open |
| 28 | 35 Bramtree CrtBrampton Industrial — Addition — Complete. |
Addition | Mar 20, 2026 | $10,255,830 | Open |
| 29 | 166 Sylvan AveToronto New gymnasium addition; interior renovation of classrooms & library — Elizabeth Simcoe Junior Public School. |
Addition/Alt | Dec 16, 2025 | $10,169,400 | Open |
| 30 | 715 Milner AveToronto Convert warehouse to new data centre; 2 new emergency generators installed on site. |
Addition/Alt | Jan 8, 2026 | $10,000,000 | Open |
Data notes: Permits sourced from Canadian municipal building records. Active permits only (open/pending/issued). Permit values are declared estimates and may not reflect final project cost. May 2026 data is partial. Coverage limited to municipalities currently reporting to RenoIntel — Toronto, Mississauga, Brampton, Sudbury.